Free PERT Estimate Calculator
Combine optimistic, most likely and pessimistic estimates into a weighted planning estimate.
Updated
What does this calculator do?
Calculate your result
Free · No account requiredYour entries stay in this browser session. Download or copy anything you want to keep.
Formula or structure
Expected duration = (optimistic + 4 × most likely + pessimistic) / 6; standard deviation = (pessimistic − optimistic) / 6
Method reference: PMI: Five keys to estimating
Worked example
Estimates of 2, 5 and 14 days produce a 6-day weighted estimate and a 2-day standard-deviation estimate.
How to use it
- Read the field descriptions and use one consistent set of units.
- Enter your own figures or select Load example to inspect a worked scenario.
- Review the result alongside the assumptions below.
- Copy or download the output, then assign the next action in your planning workflow.
Assumptions and interpretation
The three-point assumptions do not establish a delivery probability. Dependencies and correlated risks can change a project schedule.
Read the practical guideQuestions about this tool
Can I mix days and hours?
How does the pert estimate calculator work?
Do I need an account to use this tool?
Are my inputs uploaded or saved?
Related tools
Sprint Capacity Calculator
Estimate available team hours after leave and focus allocation before committing to sprint work.
ExploreMeeting Cost Calculator
Estimate the staff-time cost of a meeting using attendee count, duration and a loaded hourly cost.
ExploreSprint Velocity Calculator
Average three completed sprints and estimate how many similar sprints a remaining backlog might need.
ExploreTurn the plan into shared work
Give each next action an owner, a completion condition and a realistic date. My First Task brings tasks, boards, project workflows and issue tracking into one workspace.